What plug-in solar is, and how it works
A plug-in solar system is a solar panel or two (the common setups) and a microinverter that connect to your home through a wall outlet. It feeds power into your home's circuits, so you buy less from the grid while the sun is up.
The parts
- Panels. Often one or two, on a balcony railing, a patio, a fence or the ground.
- A microinverter. It turns the panels' direct current into household alternating current. Its AC output is what state caps measure; Vermont's law, for example, caps the combined inverter capacity per meter (Act 149).
- A plug and cord. The inverter connects to an outlet, which sellers often require to be GFCI-protected. An ordinary outlet is suitable only where the exact product, the circuit and your state's rules allow it; Maine, for example, requires a dedicated single-outlet circuit above 420 W (35-A M.R.S. § 3475).
- Sometimes a battery. Some systems, such as EcoFlow's STREAM Ultra, add a battery so solar made at noon can be used in the evening.
What shuts down during a grid outage?
The laws passed so far require the device to stop sending power to the grid when the grid goes down, so it cannot energize lines a utility crew is working on. California requires a certified isolation feature (SB 868); Vermont requires a feature that keeps the device from energizing the building (Act 149).
That outage shutoff limits backfeed to the grid. It does not cover every hazard: UL notes that power fed into a circuit can push wiring past its rating without tripping the breaker, that grid-tied inverters are not evaluated for people touching them, and that two-way current can blind a GFCI (UL). Mounting and circuit loading are separate questions too.
UL 3700, the listing several laws name, is what UL calls an Outline of Investigation for plug-in PV equipment, still under development. A listing for the inverter alone is not the same as a listing for the whole system; one seller we checked says its kit has the first and not the second.
Where the power goes
The power is used by whatever is running in your home at that moment: the fridge, a router, a computer. When the panels make more than the house uses, the surplus flows out to the grid. The laws so far are written for offsetting your own use, not selling power: Vermont's says exports are not paid for, and Connecticut's requires a warning that some meters can charge you for them (Public Act 26-127). We publish no savings estimate.
What the laws change
Without a law, a system connected to your home wiring falls under your utility's interconnection rules, the same paperwork written for rooftop arrays. The 10 enacted laws replace that, for systems under a set size, with a notice to the utility or none, from the date each exemption starts:
| State | Cap | Exemption | What your utility gets |
|---|---|---|---|
| Utah | 1,200 W | Exemption in force, May 7, 2025 | No notice is required. Utilities may not require approval, a fee or extra controls for a qualifying device. |
| Maryland | 1,200 W | Exemption in force, Jul 1, 2026 | Notify the utility before installation, and give it the system's safety certification and capacity. |
| Vermont | 1,200 W | Exemption in force, Jul 1, 2026 | No notice, approval, fee, extra controls or interconnection agreement. Devices may connect only where the home has a smart meter. The utility keeps its right to recover costs if a device overloads your service. |
| Maine | 1,200 W | Exemption in force, Jul 29, 2026 | Up to 420 W: no notice. Above 420 W: notify the utility within 30 days after installing, on the commission's form (service address, inverter capacity and a compliance statement). The utility may not require approval, an interconnection application or study, a fee or extra controls, and may not deny a compliant system. |
| Colorado | 1,920 W | Exemption in force, Aug 12, 2026 | Utilities may not require approval before you install or use a qualifying device, and no one may impose unreasonable conditions on it. The utility may ask to be told that a device is there and its size. |
| Connecticut | 1,200 W | Exemption in force, Oct 1, 2026 | Utilities may not require prior approval or charge a fee. |
| California | 1,200 W | Signed, starts later, Jan 1, 2027 | The utility may require a simple online registration (address, make, model and size) but may not require approval, a fee or extra controls. |
| New Hampshire | 1,200 W | Signed, starts later, Jan 1, 2027 | No prior approval. The utility may ask to be notified after installation. |
| Virginia | 1,200 W | Signed, starts later, Jan 1, 2027 | Under § 56-596.8, the customer notifies the utility in advance and the utility has 15 days to check the notice is complete. We have not yet read that section ourselves; this comes from the review that did. |
| New Jersey | 1,200 W | Signed, starts later, Mar 1, 2027 | No notice required. Utilities may not require prior approval, a fee or extra controls. |
Scroll the table sideways for more columns.
Before you buy
- Check your state's page for the cap, the start date and any notice you must give.
- Match the kit's AC output in your configuration, not the panel wattage, to that cap.
- Look for the listing your state names, and check whether it covers the whole system.
- If you rent, read the renter rules for your state. Some laws protect tenants, and others say nothing about them.